CESP Schedule of Works

This is a list of the roads in the CESP programme and the planned start dates. Please note this is only a guide and may change, and not all Villages' properties in Custley Hey are in the project area. If you are unsure, please contact the CESP Team on 0151 480 1313.CESP Property

Road - Planned Start Date

Woodfarm Hey - December 2011

Custley Hey - January 2012

Terret Croft - February 2012

The Close, Terret Croft - February 2012

Dannette Hey - February 2012

The Close, Dannette Hey - March 2012

The Court, Dannette Hey - March 2012

The Grove, Dannette Hey - March 2012

The Mews, Dannette Hey - March 2012

The Walk, Dannette Hey - March 2012

Boydell Close - March 2012

Little Moss Hey - April 2012

Brandearth Hey - May 2012

Round Hey - June 2012

Hollow Croft - July 2012

Boode Croft - August 2012

Boode Croft - September 2012

Boode Croft - October 2012