CESP Schedule of Works

This is a list of the roads in the CESP programme and the planned start dates. Please note this is only a guide and may change, and not all Villages' properties in Custley Hey are in the project area. If you are unsure, please contact the CESP Team on 0151 480 1313.

CESP PropertyRoad - Planned Start Date

Woodfarm Hey - December 2011
Custley Hey - January 2012
Terret Croft - February 2012
The Close, Terret Croft - February 2012
Dannette Hey - February 2012
The Close, Dannette Hey - March 2012
The Court, Dannette Hey - March 2012
The Grove, Dannette Hey - March 2012
The Mews, Dannette Hey - March 2012
The Walk, Dannette Hey - March 2012
Boydell Close - March 2012
Little Moss Hey - April 2012
Brandearth Hey - May 2012
Round Hey - June 2012
Hollow Croft - July 2012
Boode Croft - August 2012
Boode Croft - September 2012
Boode Croft - October 2012